Detention Center Budgets Proposed

An amended 2019 and proposed 2020 budget for the Lincoln Parish Detention Center were introduced and discussed in this morning’s meeting of the Detention Center Commission at the Lincoln Parish Court House.

The largest change in the 2019 amendment was the removal of revenues (and corresponding expenditures) for the construction of a 100 bed addition to the center.

Originally, the plan was to begin construction this year, but delays have forced the timetable over into 2020.

The addition will allow prisoners who are housed out of parish at extra expense to be housed locally. Considerable savings is expected.

Notable also is the reduction in the jail’s fund balance, a result of the higher construction cost of the new addition.

About $2.8 million of the construction cost is paid for by borrowed money, and the balance of the $3.7 million cost is paid from the jail’s fund balance. Warden Jim Tuten said the new building is expected to be occupied by next November.

Also significant was the estimated sales tax collections for 2019 were about $100 thousand less than projected.

A December 17, 10 AM meeting and public hearing was set for final approval of the budgets.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s


%d bloggers like this: