Ruston Sports Complex Sees Massive Cost Increase Over Estimate

The just-contracted Ruston Sports Complex that is to be built over the next two years off South Farmerville Street will cost more than double the original estimate that was sold to the voters.

Earlier this month, a $35.2 million contract was approved by the city’s Board of Aldermen to construct the facility.

When the “Moving Ruston Forward” plan was approved by the council in February, 2016, the estimated cost of the facility was said to be $15 million. The plan, along with a 3/4 cent sales tax increase to pay for it, was approved by Ruston voters in an April, 2016 election.

See here the “Moving Ruston Forward” presentation, page 25.

The construction contract does not include the cost of acquiring property for the facility. It is unclear where the money will come from for the additional cost, or what other infrastructure improvements might be left undone.

Advertisements

One Response to “Ruston Sports Complex Sees Massive Cost Increase Over Estimate”

  1. Anonymous Says:

    All within the state, nothing outside the state, nothing against the state.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s


%d bloggers like this: